| No | Client / site | Scope of work | Contract | Completed |
|---|---|---|---|---|
| 01 | Kendal Power Station | Refurbishment of potable water gravity filters 1-6 | Subcontract | Nov 2026 |
| 02 | Matimba Power Station | Replacement of sand in potable water gravity filters 1-8 | Subcontract | Jan 2026 |
| 03 | Koeberg Nuclear Power Station | Supply and delivery of 25 modified steel shipping containers | Subcontract | Nov 2024 |
| 04 | Pretoria Portland Cement, Slurry Plant | Investigation of sewage treatment plants and water softening plant | Subcontract | Apr 2024 |
| 05 | Majuba Power Station | Refurbishment of high conductivity effluent system (JV) | Direct | Feb 2023 |
| 06 | Cullinan Diamonds | Investigation of underground water seepage and solids treatment | Direct | Nov 2023 |
| 07 | Mothae Diamonds | Maintenance of potable water filters | Direct | Jan 2022 |
| 08 | Kriel Power Station | Unit 6 ash plant inspection and repairs during annual shutdown | Subcontract | Dec 2020 |
| 09 | Majuba Power Station | Refurbishment of potable water gravity filters 1-3 | Subcontract | Mar 2020 |
| 10 | Arnot Power Station | Replacement of lamella clarifier modules and steel beams | Subcontract | May 2019 |
| 11 | Blendcor | Design, supply and installation of CPI oil separation system | Subcontract | Dec 2018 |
| 12 | Majuba Power Station | Removal and installation of nozzles and distribution boxes | Subcontract | Nov 2018 |
| 13 | Vaalkop WTP, Magalies Water | Installation of new pump, pipework and concrete bases | Subcontract | Dec 2017 |
| 14 | Hendrina Power Station | Replacement of sand and filter nozzles in gravity filters 1 to 6 | Subcontract | Current |
TRACK RECORD
Proven delivery at power stations, mines and process plants
13
Referenced projects, 2017 to present
R64.5M
Approximate combined value of referenced work
6
Power stations served, including Koeberg Nuclear
LARGEST PROJECTS BY APPROXIMATE VALUE (R MILLION)
Majuba: high conductivity effluent system (JV)
23%
Kendal: gravity filters 1-6 refurbishment
15.9%
Matimba: filter sand replacement 1-8
8.5%
Majuba: gravity filters 1-3 refurbishment
5.7%
Koeberg: 25 modified shipping containers
4.3%
Blendcor: CPI oil separation system
2.7%
Majuba: nozzles and distribution boxes
1.45%
Arnot: lamella clarifier modules
1.15%
TRACK RECORD
Proven delivery at power stations, mines and process plants
13
Referenced projects, 2017 to present
R64.5M
Approximate combined value of referenced work
6
Power stations served, including Koeberg Nuclear
LARGEST PROJECTS BY APPROXIMATE VALUE (R MILLION)
Majuba: high conductivity effluent system (JV)
23%
Kendal: gravity filters 1-6 refurbishment
15.9%
Matimba: filter sand replacement 1-8
8.5%
Majuba: gravity filters 1-3 refurbishment
5.7%
Koeberg: 25 modified shipping containers
4.3%
Blendcor: CPI oil separation system
2.7%
Majuba: nozzles and distribution boxes
1.45%
Arnot: lamella clarifier modules
1.15%